Project objectives: Design,
execution, testing and monitoring of a functional model of a HWG equipped
with energy management system, dedicated to vertical axis HWT, having a
total output power (electric and thermal) of 3 kW.
Project phases and dead-lines:
Phase I. Analysis of feasible
constructive solutions of components for vertical axis HWT (15.12.2014)
Phase II.
Design and execution of experimental models of the HWG and of the energy
management system (15.12.2015)
Phase III.
Acomplishing the design of HWG and of energy management system and partial
execution of HWG (15.12.2016)
Phase IV. Execution of
experimental models, their testing and monitoring (30.09.2017)
Aimed results:
-At least 2 patent demands submitted at OSIM
-At least 4 scientific articles/papers published in ISI Journals or ISI Proceedings
-Functional model of a HWG equipped with energy management system
|